Expedited Replacement Screw Saves JBS Downtime
Introduction
JBS operates a large beef processing facility in Cactus, Texas. Over 5,000 head of cattle are processed per day, producing millions of pounds of beef for human consumption including prime cuts and ground beef. Meat byproducts are almost exclusively handled with screw conveyors and represent a very large part of the operation.
Challenge
JBS scheduled maintenance work during the 4th of July weekend and urgently needed a replacement screw for conveying bone meal. Motion in Amarillo, Texas contacted KWS because of our reputation for delivering high quality parts and systems on short notice. The planned maintenance window created a firm deadline, and any delay in receiving the screw could have extended the outage or impacted plant operations.
KWS Advantage
KWS immediately expedited the order through production. With millions of dollars in raw material inventory on hand, KWS can start manufacturing within hours of receiving an order. The Made-to-Order screw was manufactured, shipped, and delivered in only three working days. KWS understands the importance of planned downtime and works closely with distributors such as Motion to support critical maintenance schedules. When fast delivery and dependable manufacturing are required, KWS provides the service and execution customers need.
KWS Manufactured and Delivered Replacement Screw in 3 Days
Manufacturing Begins Immediately After Receiving Order